The following guest article was submitted by Mikheil Shengelia, Research Analyst at Eagle Alpha, an alternative data aggregation platform providing supporting advisory services for data buyers and vendors. It was written in collaboration with SupplyMaven, a supply chain risk and economic activity data provider.
Data center connection queues now run to hundreds of gigawatts, yet little of that shows up in metered load. The exception is Northern Virginia, where energized demand is still growing near its fastest rate since 2022 and has outgrown the rest of its grid in every month since January 2023. The growth is always-on: the zone’s overnight floor has risen almost megawatt for megawatt with its average.
The Question
Connection queues have grown far faster than any grid can build. ERCOT was tracking about 438 gigawatts of large-load requests by June 2026, up from more than 225 gigawatts the previous December, and said the vast majority had no studies submitted. By August, the Texas governor put the figure at about 474 gigawatts, roughly 90% of its data centers. Dominion has told Virginia regulators it has about 25 gigawatts of requests with projected connection dates through the end of 2031, and about 45 gigawatts more without dates. On August 3rd, Texas halted new data center grid approvals pending an audit. On 21 September, the governor extended the halt to every state permit sought by a data center.
Queues measure intent and meters measure what is running. With connection waits lengthening and Texas frozen, the question for investors is how much of the build-out is actually arriving on the grid, and whether it is slowing. Three answers are possible:
- Accelerating. Energized load grows faster each year as the pipeline converts.
- Plateauing. Connection limits cap what arrives, and growth levels off.
- Fading. Growth rolls over as projects stall or cancel.
The metered data places Northern Virginia between the first two. Growth stepped up in 2024 and has held near its highest rate since. It is not fading. Outside Northern Virginia, zone-level meters do not yet show the build-out at all.
In Eagle Alpha’s upcoming webinar on October 22nd, we will be joined by Third Bridge, Particle, and CEO Interviews to discuss how LLMs reshape how firms process text, news, filings, and transcripts. Turning raw, messy text into reliable, investable signals is far from simple, and the rapid rise of large language models has brought both new possibilities and new complications. Click here to register.
SupplyMaven
SupplyMaven is a supply chain risk intelligence platform. It maintains series on power, freight, and industrial activity, including hourly grid load for US data center hubs, and delivers them under license through its API. This piece draws on the available grid series.
Public grid data is free. Usable grid data is not. The US Energy Information Administration publishes zone-level demand about 51 hours late, and the most recent days arrive incomplete while looking complete. Handled naively, those two facts turn +31.9% growth in Northern Virginia’s overnight floor into +41.7%. The series in this piece is correct for both.
Data and Method
Source. EIA-930 hourly electricity demand by balancing authority subregion, January 2022 to August 2026 for monthly figures, with daily data through 19 September 2026. Northern Virginia’s data centers sit in the Dominion zone of PJM, which covers most of Virginia and part of north-eastern North Carolina. It is the smallest published unit that contains the cluster, so it is the measured series throughout; the figures label it Northern Virginia for brevity. Dallas-Fort Worth is the North Central zone of ERCOT. Chicago is the ComEd zone of PJM. Months are UTC calendar months.
Overnight floor. The minimum hourly demand for each day, keeping only days with 20 or more hours reported. Data centers draw power around the clock, so floor growth tracks always-on load.
Trailing 12-month growth. The latest 12 months’ average demand against the 12 months before, day-weighted. A full year averages out a full weather cycle.
Share of grid. A zone’s demand as a share of its parent grid, as a ratio of sums on matched hours. Rest of PJM is PJM total minus the Dominion zone on the same hours.
Weather. Metered figures are published unchanged. Weather is an independent check using NOAA daily temperatures at Washington Dulles, Dallas-Fort Worth, and Chicago O’Hare airports. A month is flagged when its average temperature differs from the same month a year earlier by more than 3.0 F, a rule fixed before the load data was compared. Flags are common: 21 of 44 months at Dulles, 20 at Dallas-Fort Worth and 18 at O’Hare. Trends are read with flagged months marked, not removed.
Data handling. Counting EIA’s partial recent days as complete inflated the 2026 year-to-date Dominion overnight floor by 7.2% (15,621 MW against 14,571 MW on full days only). Combined with a full-year against part-year comparison, the same error produces +41.7% floor growth from 2022 to 2026. The correct like-for-like figure is +31.9%. EIA also leaves gaps it never fills: in August 2026 it published no data at all for two full days in the Dallas zone.
Evidence
Northern Virginia is not slowing
Dominion zone trailing growth was +1.2% in December 2023. It reached +6.3% by June 2024, +6.9% by December 2024 and +8.5% by December 2025. In August 2026 it stood at +8.2%. Over the latest 12 monthly readings, trailing growth ran between +6.7% and +8.5%, with the overnight floor between +8.1% and +10.3%. A year earlier the range was +5.6% to +8.4%. The rest of PJM ran between +1.6% and +3.0%.
August 2026 demand was up 17.3% on the year, but that is weather: August 2026 was 5.3 F warmer than August 2025 at Dulles, and August 2025 had itself been 4.8 F cooler than the year before. Both months are flagged. That single month lifts the latest trailing reading, which is why the range is the better guide than the endpoint.
June and July 2026 were each up 3.7% in the year, well below the trailing rate. Neither month is flagged at Dulles, where both were about 1 F cooler than a year earlier. But the rest of PJM fell 2.7% and 2.0% in the same months, so the Dominion zone still outgrew its grid by about six points in each. The softness was grid-wide, not local.
Every month, the Dominion zone outgrew the rest of PJM
In all 44 months from January 2023 to August 2026, Dominion zone demand grew faster year on year than the rest of PJM, and its share of PJM rose. The smallest monthly share gain was 0.11 percentage points. Because the zone and the rest of PJM largely share the same weather systems, the gap is less weather-exposed than either series alone. In the 23 months with no weather flag in Dulles, it never fell below 1.0 point.
Always-on load rose almost megawatt for megawatt with the average
From December 2022 to August 2026, trailing average demand rose from 13,112 MW to 16,199 MW, an increase of 3,087 MW. The overnight floor rose from 10,982 MW to 14,097 MW, up 3,115 MW. In the last 12 months alone, the average added 1,226 MW and the floor 1,186 MW. Weather-driven growth lifts peaks more than troughs. Here the trough moved as much as the average, which is the signature of always-on load.
Same-month comparisons confirm it. From January to August 2026, compared with the same months in 2022, average demand rose 3,503 MW (+26.4%) and the floor rose 3,500 MW (+31.9%). April and May alone, spring months when heating and cooling loads are lowest, show the floor up 32.1% and the average up 27.4%. Compared with January to August 2025, the Dominion zone average rose 7.7% and the floor 8.5%, while the rest of PJM rose 1.7%.
Over full years, 2022 to 2025, the Dominion zone added 2,287 MW (+17.4%). The rest of PJM added 1,528 MW (+1.9%), and PJM as a whole 3,788 MW (+4.1%). About 60% of PJM’s added load came from a zone carrying about 15% of its load. The zone’s share of PJM, January to August, rose from 14.0% in 2022 to 16.7% in 2026.
Dallas and Chicago do not show it at zone level
Dallas-Fort Worth’s trailing share of ERCOT fell from 29.83% in December 2022 to 27.88% in August 2026. Chicago’s share of PJM fell from 11.75% to 11.14%.
Over the last 12 months, Dallas grew 4.8% against 4.6% for the rest of ERCOT, so it held its share of the grid rather than gaining it. The trailing share has recovered from a low early this year, but January, February, March and August 2026 are all weather-flagged at Dallas-Fort Worth, so that recovery is not yet readable as a turn. Chicago’s trailing growth in August 2026 was +0.4%, against +2.9% for PJM excluding the Dominion and Chicago zones.
This does not mean data centers are absent in either hub. Both zones are large and mixed, so data center load does not dominate them as it does in the Dominion zone. Some major Texas projects also sit outside the Dallas zone, for example Abilene.
Queue Against Meter
Virginia’s queue is the clearest published example of the gap. A State Corporation Commission hearing reported in July showed that Dominion can study and approve about 10 requests a year while about 10 new ones arrive each month. It has approved 111 projects to connect by the end of 2031; 220 more are waiting, requesting 50 gigawatts.
Figure 5. The queue and the meter
| Northern Virginia (Dominion zone) | Texas (ERCOT) | |
| In the pipeline | About 25 GW with connection dates through 2031 and about 45 GW more without dates (February 2026 filing). 111 projects approved to connect by the end of 2031; 220 more waiting, requesting 50 GW. | About 438 GW of large-load requests in June 2026 (ERCOT), about 474 GW by August (governor’s letter, citing ERCOT), roughly 90% of its data centers. ERCOT says the vast majority have no studies submitted. |
| Pace | About 10 requests studied and approved a year; about 10 new requests arriving each month. | New grid approvals halted August 3rd pending audit, which ERCOT can apply to loads of 75 MW or more; all state permits halted 21 September. Before the halt, ERCOT expected about 3.9 GW of large load to energize in Q4 2026, 841 MW of it in the North Central zone. |
| Arrived | Metered average load up 1,226 MW in the 12 months to August 2026, and 3,087 MW since December 2022. | 5,302 MW of large loads approved and observed energized since 2022, as of 18 November 2025. |
| Hub share of grid | Dominion zone 14.0% to 16.7% of PJM, January to August 2022 to 2026. | Dallas-Fort Worth zone 29.83% to 27.88% of ERCOT, trailing 12 months, 2022 to 2026. |
Source: SupplyMaven analysis of EIA-930 hourly demand; Dominion filing to the Virginia State Corporation Commission as reported by Virginia Business (February 2026); Prince William Times (July 2026); ERCOT board materials (June 2026), news release (December 2025) and Large Load Interconnection Process Q&A (December 2025); Office of the Texas Governor (August and September 2026); Houston Public Media (September 2026). Pipeline figures are contracted or requested capacity; metered figures are average draw. The two are not directly comparable, since data centers ramp over years and rarely run at full contract. ERCOT’s energized figure covers all large loads, not only data centers.
Northern Virginia’s approved pipeline is arriving on the meter, steadily and without a break, even as Dominion slows new approvals. Texas shows the opposite gap: a queue that roughly doubled between December and August, a few gigawatts energized, and a Dallas zone that has lost share of its grid since 2022.
The Texas freeze acts on what is not yet built. Loads already connected keep running and keep showing on the meter. The September order goes further than August’s, covering state permits such as water use and on-site power plants, so projects that hold grid approval but still need a permit now wait too.
What This Means for Investors
The metered series is an independent read on the build-out, separate from queue announcements and company guidance. It speaks most directly to four exposures:
- The regulated utility serving the zone. Dominion Energy’s shareholders approved its combination with NextEra Energy on September 3, 2026, and the transaction now awaits regulatory approvals, including from the Virginia State Corporation Commission. The metered series is a monthly read on the load growth the acquirer is buying, and on whether Dominion’s slower approvals show up in the zone’s growth rate.
- Independent power producers selling into PJM, where one zone supplied about 60% of load growth from 2022 to 2025.
- Power equipment suppliers, where conversion of the queue into connected load drives orders.
- The hyperscaler capex debate, where the meter shows whether committed spending is turning into running load, and where.
Texas is now an experiment. A queue can carry a stalled project for years; a meter counts only what runs. If the freeze holds, the Dallas-Fort Worth zone’s share of ERCOT will show it. Before the halt, ERCOT expected about 3.9 gigawatts of large load to energize in the fourth quarter of 2026, with 841 megawatts in the North Central zone. Whether that arrives is the first test.
Nothing here asserts a link between load growth and any share price.
Limitations
Behind-the-meter generation is invisible in grid data, and the Texas order now covers on-site power permits. Zones are larger than the counties where data centers cluster; the Dominion zone covers most of Virginia. Load days are UTC while temperatures are local days. Most of the history is rebuilt from EIA’s currently published series and EIA revisions are not retained, so this is not a record of data as first published. Outside Northern Virginia, the zones are too mixed to isolate data center load.
Summary
The build-out is real, and in Northern Virginia it is coming online at a steady pace. Trailing growth has held between 6.7% and 8.5% for a year, always-on load has risen almost megawatt for megawatt with the average, and the zone has outgrown the rest of PJM in every month since January 2023, including this summer’s cool months. Elsewhere, zone-level meters do not yet show it. Queues hold hundreds of gigawatts of intent; the meters show a few gigawatts of arrival.
The forward question is whether Northern Virginia’s lead narrows as Dominion slows approvals, and whether the Texas freeze shows first in the queue or on the meter. The checkpoints:
- Each monthly EIA update of Dominion zone trailing growth, overnight floor and lead over the rest of PJM in unflagged months.
- TCEQ’s compliance update to the Texas governor, due 19 October 2026, and completion of the PUCT and ERCOT audit.
- Whether the roughly 3.9 gigawatts of large load ERCOT expected to energize in the fourth quarter of 2026, 841 megawatts of it in the North Central zone, arrives on the meter under the freeze.
- Whether the Dallas-Fort Worth or Chicago share of grid turns up in unflagged months.
In Eagle Alpha’s upcoming webinar on October 22nd, we will be joined by Third Bridge, Particle, and CEO Interviews to discuss how LLMs reshape how firms process text, news, filings, and transcripts. Turning raw, messy text into reliable, investable signals is far from simple, and the rapid rise of large language models has brought both new possibilities and new complications. Click here to register.